Project Description

Mine Shaft Specialist Engineering

RKF Engineering Services was engaged by our client, a Canadian mining company, during the construction phase of two 1km deep mine shafts in Canada. Our client had discovered that there were cracks developing in the temporary shaft lining, which was being completed during the initial boring, above the boring machine.

Our brief was to inspect the lining, determine the root cause of the cracking and propose changes to the construction to eliminate further cracking.

With over 28 years of experience in concrete technology, RKF Engineering Services was well positioned to assist on this project.

Our initial inspection found that the root causes of the cracking were: the effect of frozen ground on the lining before the concrete set; poor concrete mix design due to ambient conditions; and poor curing of the lining.

RKF Engineering Services worked with the client and contractors and audited the entire concreting process – from the batch plant to the site – and provided advice and direction to improve the concrete mix design, batching, delivery and curing. As part of the work, the initial shotcrete construction was changed to formed cast in situ concrete using a high durability, high flow, high strength concrete.

From the work done to date the new mix designs are now achieving the strengths required for design, the batching and delivery of the concrete is now occurring at a much faster pace and the quality of the overall construction has dramatically improved. The shaft is now being constructed at approximately 9 times the speed of the old construction and no further damage of the lining has been reported.

For further information on this project or in general, phone +61 2 4225 7519 or send us an email.